§ 155.18 REVIEW AND APPROVAL.
    Each application for site development approval shall be reviewed and acted upon according to the following procedures.
   (A)   Construction plans shall be received by the MS4 Department for review by the MS4 Department and/or the consultant retained by the MS4 Department, and the review and inspection fees will be remanded to the Storm Sewer Operating Account numbered 101019319. Upon preliminary review, the MS4 Department shall determine:
      (1)   The submittal is complete and sufficient pursuant to §§ 155.35 through 155.43 and direct the specific review of the submittal; or
      (2)   The submittal is deficient and lacks information pursuant to §§ 155.35 through 155.43 and therefore can not be adequately reviewed; at which time:
         (a)   The developer will receive written notice of those specific deficiencies of the submittal; and/or
         (b)   Be invited to meet with the county or its qualified representative to discuss specific deficiencies of the submittal.
   (B)   Construction plan review shall be carried out within the number of work days shown in Table 1. If there has been no notification or request for more information within that time, application shall be assumed complete and approved on the following workday.
   (C)   Upon completion of a review, the applicant shall be notified in writing that the submitted construction plan:
      (1)   Fulfills the requirements of this chapter and constitutes site development approval so long as a notice of intent is submitted to the MS4 Department and IDEM at least four hours prior to commencement of construction activities; or
      (2)   Does not meet the requirements of this chapter and therefore does not warrant the issuance of a site development approval.
(Ord. 2008-07, passed 5-5-2008; Ord. 2020-05, passed 9-28-2020)