6-2-7: COST PARTICIPATION FOR LARGER MAINS:
Except in such instances where a single sewer district, subdivision, or development under one ownership shall require a sewer main greater than eight inches (8") in diameter, the Town shall participate in the cost of installing larger sized sewer mains. The extent of Municipal participation shall be based on the following percentages of the total cost of sewer mains greater than eight inches (8") in diameter:
 
Size Of Main
Percentage Of Municipal Participation
10 inches
 
15%
12 inches
 
25%
15 inches
 
35%
18 inches
 
45%
18 inches or larger
 
To be determined by Town
 
In those instances where a district, subdivision or development under one ownership is of such size that sewer mains larger than eight inches (8") in diameter are required, the entire cost of such oversize sewer mains shall be paid by the district or subdivider. (Ord. 90-03, 11-27-1990)