§ 155.181 IMPLEMENTATION OF CONDITIONAL USE PERMIT (CUP).
   Unless the Town Council issues a conditional use permit which either is specifically exempt from any time constraints or has some other specified time period for implementation, the applicant must secure a valid building permit within a 12-month period from date of issuance of the conditional use permit. In addition, if the project for which a CUP was issued is not complete and a valid building permit is not in place at the end of said 12-month period, the Zoning Administrator shall notify the applicant of either such finding, and within 60 days of said notification, the Planning Board shall make a recommendation concerning the rescission of the conditional use permit to the Town Council. The Town Council, after having conducted a public hearing to consider the rescission, may then rescind the conditional use permit, or extend the life of the conditional use permit for a specified period of time. Due notice of said public hearing shall be given as prescribed in § 155.173 of this chapter.
(Ord. passed - -, § 9.12)