EXHIBIT II: ELECTRIC SUPPLY RATES
RATE ADJUSTMENT (Applicable to Rates RS, SGS, LGS, P, IP, SMS, LMS, S and SLS)
   The Rate Adjustment shall be on the basis of a Purchased Power Cost Adjustment Tracking Factor, occasioned solely by changes in the cost of purchased power:
      The Rate Adjustment applicable to the above listed Rate Schedule shall be ($0.0002748) kwh used per month.
   To be applied for service provided from July 1, 2018 through June 30, 2019.
FUEL COST ADJUSTMENT (Applicable to Rates RS, SGS, LGS, P, IP, SMS, LMS, S and SLS)
   The Fuel Cost Adjustment in dollars per kilowatt hour shall be the same as the most recently billed to the Avilla Municipal Electric Utility by its purchased power supplier per kilowatt hour, adjusted for the current line loss factor and the collection of applicable utility receipts tax.
(Res. 688-7-18, passed 7-18-2018)