An application for approval of a transmission tower (other than a cellular antenna tower) shall include the following:
(A) A site plan or plans drawn to scale and identifying the site boundary; towers; guy wire anchors; existing and proposed structures; vehicular parking and access; and existing vegetation to be retained, removed or replaced;
(B) Uses, structures and land use designations on the site and abutting parcels; and
(C) A copy of the contract(s) with an owner(s) of property upon which the transmission tower is to be constructed which shall include a provision that specifies, in the case of abandonment, a method that the owner (operator) will follow in dismantling and removing the transmission tower, including a timetable for removal if necessary.
(Ord. 2002-07, passed 11-11-02)