(a) Street Grading. No street grading shall be permitted until the final construction plans have been approved by the Village Engineer and inspection fees have been paid. No street grading shall be commenced without three (3) working days notice to the Village Engineer.
(b) Street Subgrade. All streets shall be graded to their full width, including side slopes. No obstructions shall be placed or allowed to remain in the street right-of-way. The subgrade shall be free of sod and/or vegetative or organic matter. Soft clay and other unsuitable material shall be cleared to a depth as determined by the Village Engineer. The subgrade shall be shaped and compacted subject to the requirements of the Village Engineer, and no fill shall be placed until said subgrade has been inspected and approved.
(c) Pavement Application. No pavement shall be placed until the prepared subgrade has been inspected and approved. The finish pavement course shall not be placed over the base course until a period of time as specified by the Village Engineer has elapsed. All failures in the base course must be repaired prior to installation of the finish course.
(d) Street Signs. The Owner/Developer shall provide and install street name and parking signs at intersections and other locations as designated by the Planning and Zoning Board. The material, graphics and content are subject to approval by the Planning and Zoning Board.