§ 152.05 APPROVAL OF PLANS.
   (A)    A manufactured home park plan meeting the requirements of § 152.04 shall be submitted for review and approval by the Planning Board before any improvements are made to land proposed for a manufactured home park. This plan shall be submitted to the County Planner in eight copies at least 15 days before the meeting of the Planning Board at which it is to be reviewed.
   (B)   The Planning Board shall review this plan for any changes required in order that the manufactured home park may comply with this chapter. After revisions in the plan, if required, the Planning Board will take formal action within two regularly scheduled meetings after the meeting at which the plan was first reviewed. Failure to take formal action within this time period shall have the same effect as a recommendation that the plan be approved. Within five days after its final action on the plan, the Planning Board shall notify the builder/ developer by letter of its recommendation. Within ten days after final approval the builder/developer shall pay the required fees and file a copy of the approved plan with the County Building Inspector.
   (C)   Every decision of the Planning Board shall be subject to review at the request of the aggrieved party by the Board of Adjustment. The appeal to the Board of Adjustment must be filed within 30 days from the notification of the Planning Board's action.
(Ord. passed 10-19-09; Am. Ord. passed 5-15-23)