§ 156.56 INSTALLATION OF IMPROVEMENTS.
   Prior to the approval of the final plat, the subdivider shall have complied with the following requirements:
   (A)   Streets and storm drainage facilities. All streets and storm drainage facilities in the residential subdivision shall have been constructed in accordance with the drawings submitted.
   (B)   Water supply. Where public water is reasonably accessible (actually available and not cost prohibitive), the subdivider shall connect with the public supply and provide water mains and a suitable water connection to each lot. Where a public water supply is not reasonably accessible, the subdivider may provide individual water supplies or a community water system.
   (C)   Sewage systems. Where a public sanitary sewer system is reasonably accessible (actually available and not cost prohibitive), the subdivider shall connect with the public system and shall provide a connection for each lot. Where a public sanitary sewer is not accessible, individual sewage disposal systems or a community sewage disposal system may be provided. These systems shall be located, constructed, and operated in accordance with the requirements and standards of the North Carolina Department of Environment, and Natural Resources; the North Carolina Division of Health Services; and the Appalachian District Health Department.
   (D)   Installation at time of final plat. In the event that any public or community utilities are not installed at the time of final plat approval, a bond or other security guarantee may be required by the Planning Board as specified in § 156.57.
(Ord. passed 3-20-96; Am. Ord. passed 12-19-22; Am. Ord. passed 8-21-23) Penalty, see § 156.99