(A) Upon proper application, the utility will provide necessary overhead distribution and service facilities for rendering service. A contribution or minimum guarantee will be necessary when the estimated revenue for a two and one-half year period is less than the estimated cost of such facilities. At request of customer for extension of distribution lines to be underground, the utility will estimate the installation cost for overhead facilities and estimate the installation cost for underground facilities. The customer shall be responsible for the difference in cost between overhead facilities and underground facilities when the estimated cost for underground facilities is greatest.
(B) One MW or greater services. The utility may enter a contract agreement with any applicant with an average billing demand of 1 MegaWatt or greater for interconnection terms and conditions and applicable costs associated with the interconnection.
(Ord. 2018-1, passed 3-21-2018)