§ 152.04 DEFINITIONS.
   For the purpose of this chapter, the following definitions shall apply unless the context clearly indicates or requires a different meaning.
   APPEAL. A request for review of the Floodplain Administrator’s interpretation of any provision of this chapter or a request for a variance.
   AREA OF SPECIAL FLOOD HAZARD. The land in the floodplain within a community subject to a 1% or greater chance of flooding in any given year. The area may be designated as Zone A on the Flood Hazard Boundary Map (FHBM). After detailed rate making has been completed in preparation for publication of the FIRM, Zone A usually is refined into Zones A, AE, AH, AO, A1-99, VO, V1-3O, VE, or V.
   BASE FLOOD. The flood having a 1% chance of being equaled or exceeded in any given year.
   CRITICAL FEATURE. An integral and readily identifiable part of a flood-protection system without which the flood protection provided by the entire system would be compromised.
   DEVELOPMENT. Any human-made change in improved and unimproved real estate including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation, or drilling operations or storage of equipment or materials.
   ELEVATED BUILDING.
      (1)   A non-basement building built:
         (a)   In the case of a building in Zones A1-30, AE, A, A99, AO, AH, B, C, X, and D, to have the top of the elevated floor or (in the case of a building in Zones V1-30, VE, or V) to have the bottom of the lowest horizontal structure member of the elevated floor elevated above the ground level by means of pilings, columns (posts and piers), or shear walls parallel to the floor of the water; and
         (b)   Adequately anchored so as not to impair the structural integrity of the building during a flood of up to the magnitude of the base flood.
      (2)   In the case of Zones A1-30, AE, A, A99, AO, AH, B, C, X, and D, ELEVATED BUILDING also includes a building elevated by means of fill or solid foundation perimeter walls with openings sufficient to facilitate the unimpeded movement of floodwaters.
      (3)   In the case of Zones V1-30, VE, or V, ELEVATED BUILDING also includes a building otherwise meeting the definition of ELEVATED BUILDING, even though the lower area is enclosed by means of breakaway walls if the breakaway walls meet the standards of § 60.3(e)(5) of the National Flood Insurance Program regulations.
   EXISTING CONSTRUCTION. For the purposes of determining rates, structures for which the start of construction commenced before the effective date of the FIRM or before January 1, 1975, for FIRMs effective before that date. EXISTING CONSTRUCTION may also be referred to as EXISTING STRUCTURES.
   FLOOD or FLOODING. A general and temporary condition of partial or complete inundation of normally dry land areas from:
      (1)   The overflow of inland or tidal waters; and
      (2)   The unusual and rapid accumulation or runoff of surface waters from any source.
   FLOOD MAP (FIRM). An official map of a community on which the Federal Emergency Management Agency has delineated the boundaries of the flood, mudslide (such as mud flow), and related erosion areas having special hazard have been designated as Zone A, M, and/or E.
   FLOOD PROTECTION SYSTEM. Those physical structural works for which funds have been authorized, appropriated, and expended and which have been constructed specifically to modify flooding in order to reduce the extent of the areas within a community subject to a special flood hazard and the extent of the depths of associated flooding. Such a system typically includes hurricane tidal barriers, dams, reservoirs, levees, or dikes. These specialized flood-modifying works are those constructed in conformance with sound engineering standards.
   FLOODPLAIN or FLOOD-PRONE AREA. Any land area susceptible to being inundated by water from any source. (See FLOOD or FLOODING.)
   LEVEE. A human-made structure, usually an earthen embankment, designed and constructed in accordance with sound engineering practices to contain, control, or divert the flow of water so as to provide protection from temporary flooding.
   LEVEE SYSTEM. A flood-protection system which consists of a levee or levees and associated structures, such as closure and drainage devices, which are constructed and operated in accordance with sound engineering practices.
   LOWEST FLOOR. The lowest floor of the lowest enclosed area, including basement. An unfinished or flood-resistant enclosure, usable solely for parking of vehicles, building access, or storage in an area other than a basement area is not considered a building’s LOWEST FLOOR provided that such enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirement of § 60.3 of the National Flood Insurance Program regulations.
   MANUFACTURED HOME. A structure transportable in one or more sections which is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities. For floodplain management purposes, the term MANUFACTURE HOME also includes park trailers, travel trailers, and other similar vehicles placed on a site for greater than 180 consecutive days. For insurance purposes, the term MANUFACTURED HOME does not include park trailers, travel trailers, and other similar vehicles.
   MEAN SEA LEVEL. For purposes of the National Flood Insurance Program, the National Geodetic Vertical Datum (NGVD) of 1988 or other datum to which base flood elevations shown on a community’s Flood Insurance Rate Map are referenced.
   NEW CONSTRUCTION. For floodplain management purpose, structures for which the start of construction commenced on or after the effective date of a floodplain management regulation adopted by a community.
   START OF CONSTRUCTION. For other than new construction or substantial improvements under the Coastal Barrier Resources Act (Pub. Law No. 97-348), includes substantial improvement and means the date the building permit was issued provided that the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days of the permit date. The ACTUAL START means either the first placement of permanent construction of a structure on a site such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation (such as clearing, grading, and filling) nor does it include the installation of streets and/or walkways nor does it include excavation for basement, footings, piers, or foundations or the erection of temporary forms nor does it include the installation on the property of accessory buildings (such as garages or sheds not occupied as dwelling units or not part of the main structure). A SUBSTANTIAL IMPROVEMENT is considered to occur when the alteration of any wall, ceiling, floor, or other structural part of the building commences, whether or not that alteration affects the external dimensions of the structure.
   STRUCTURE. A walled and roofed building including a gas or liquid storage tank that is principally above ground as well as a manufactured home.
   SUBSTANTIAL IMPROVEMENT. Any repair, reconstruction, or improvement of a structure, the cost of which equals or exceeds 50% of the market value of the structure either before the improvement or repair is started or, if the structure has been damaged and is being restored, before the damage occurred. For the purpose of this definition, SUBSTANTIAL IMPROVEMENT is considered to occur when the alteration of any wall, ceiling, floor, or other structural part of the building commences whether or not that alteration affects the external dimensions of the structure. The term does not, however, include either any project for improvement of a structure to comply with existing state or local health, sanitary, or safety code specifications which are solely necessary to assure safe living conditions or any alteration of a structure listed on the National Register of Historic Places or a State Inventory of Historic Places.
   VARIANCE. A grant of relief to a person from the requirements of this chapter when specific enforcement would result in unnecessary hardship. A VARIANCE, therefore, permits construction or development in a manner otherwise prohibited herein. (For full requirements, see § 60.6 of the National Flood Insurance Program regulations.)
   VIOLATION. The failure of a structure or other development to be fully compliant with the community’s floodplain management regulations. A structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in the National Flood Insurance Program § 60.3 (b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5) is presumed to be in VIOLATION until such time as that documentation is provided.
   WATER SURFACE ELEVATION. The height, in relation to the National Geodetic Vertical Datum (NGVD) of 1988 or other datum, where specified, of floods of various magnitude and frequency in the floodplains of coastal or riverine areas.
(Prior Code, § 4-19)