§ 152.16  USE OF PUBLIC ROADS.
   The applicant shall identify all state and local public roads to be used within the municipality to transport equipment and parts for construction, operation or maintenance of the wind energy facility.
   (A)   The Township Engineer or a qualified third party engineer hired by the township and paid for by the applicant, shall document road conditions prior to construction. The engineer shall document road conditions again 30 days after construction is complete or as weather permits.
   (B)   The township will require that the road be bonded in compliance with state regulations to ensure the prompt repair of damaged roads. The developer/permittee shall comply with all other township ordinances with respect to public roads.
   (C)   Any road damage caused by the applicant or its contractors shall be promptly repaired at the applicant’s expense.
(Ord. 5-2006, passed 12-7-2006)