9-15-5: APPROVAL OF PUD; CONDITIONS:
   A.   Conditions Of Approval: As part of its approval of a planned unit development, the council may require the applicant to meet the following conditions (among others it deems appropriate):
      1.   That the proponents of the planned unit development have demonstrated to the satisfaction of the council that they are financially able to carry out the proposed project.
      2.   That the proponents intend to start construction within one year of either the approval of the project or of any necessary zoning district change.
      3.   That the proponents intend to complete construction of the project, or approved stages thereof, within four (4) years from the date construction begins.
      4.   That the development is planned as one land use complex rather than as an aggregation of individual and unrelated buildings and uses.
   B.   Compliance With Approved Plans: Upon the council's approval of a planned unit development, construction shall proceed only in accordance with the approved plans and specifications, and in conformity with any conditions of approval.
   C.   Amendments To Approved Plans: Amendment to approved plans and specifications for a planned unit development shall be obtained only by following the procedures here outlined for first approval. (Ord. 2002-02, 1-17-2002)