§ 150.058 BUILDING INSPECTIONS.
   (A)   The Building Commissioner shall be responsible for the completion of all required inspections which shall be indicated on the building permit card.
   (B)   The permittee shall contact the Department and schedule an inspection when work, for which an inspection is required or requested by the Building Commissioner, is complete, and such notice shall be given as follows:
      (1)   Four hours prior to the earliest time an inspection is requested for footers, foundations, or concrete slabs.
      (2)   For all other inspections, notice must be provided no less than 24 hours before an inspection is requested.
      (3)   Inspections of all framing, fire blocking, bracing, all pipes, chimneys, rough electric, rough plumbing, and all heating wires, pipes, and venting shall be performed during one inspection. The Department shall not schedule inspections for any of the above mentioned components separately.
   (C)   The Department shall endeavor to schedule all inspections as requested; however, priority is given to inspections which involve an immediate life safety issue and on a first call-in basis.
   (D)   If a footer, foundation, or slab inspection has not been completed within one hour of the time set by the Department, the permittee may pour concrete and continue work on the footer, foundation, or slab provided the work has been completed in compliance with applicable law.
   (E)   (1)   The Department may assess a re-inspection fee for:
         (a)   Requested footer, foundation, or slab inspections not cancelled at least one hour prior to the earliest scheduled time requested for an inspection;
         (b)   Other requested inspections not canceled at least three hours prior to the earliest scheduled time requested for an inspection;
         (c)   Work not completed by the time requested for inspection;
         (d)   Work not in compliance with applicable codes.
      (2)   The re-inspection fee shall be paid prior to a re-inspection being scheduled.
   (F)   The Building Commissioner shall note the passing of each inspection, or the deficiencies and/or corrective work required, on the permit card at the time of inspection. A re-inspection shall be requested by the permittee once corrective work is completed and must pass inspection prior to any additional work being completed which would affect the completion of the required inspection. The Building Commissioner may require engineering analysis at the expense of the permittee to certify that the work has been completed in compliance with applicable law.
(Ord. 2017-11, passed 8-14-2017; Ord. 2018-7, passed 6-25-2018)