17.04.112   PAD CERTIFICATION.
   .010   Upon completion of the rough grading work and prior to issuance of any building permit, the City Engineer shall require submittal of the following reports and drawings, and any supplements thereto:
   .0101   A certification from the Civil Engineer that the building pad area is graded in accordance with the approved plans;
   .0102   A soil grading report prepared by the soil engineer, including locations and elevations of field density tests, summaries of field and laboratory tests, final description of the soils of the site, and other substantiating data and comments on any changes made during grading, and their effect on the recommendations made in the original report. The soil engineer shall provide certification as to the adequacy of the site for the intended use. (Ord. 5966 § 15; April 26, 2005.)