15.07.050 GENERAL REQUIREMENTS.
   .010   The owner of each building within the scope of this chapter shall cause a structural analysis of the building to be made by a civil or structural engineer or architect licensed by the State of California. If the building does not meet the minimum earthquake standards specified in this chapter, the owner shall either cause it to be structurally altered to conform to such standards; or cause the building to be demolished.
   .020   The owner of a building within the scope of this chapter shall comply with the requirements set forth above by submitting to the Building Official for review within the stated time limits:
   (a)   Within two hundred seventy days after the service of the order, a structural analysis, which is subject to approval by the building official, and which shall demonstrate that the building meets the minimum requirements of this chapter; or
   (b)   Within two hundred seventy days after the service of the order, the structural analysis and plans for the proposed structural alterations of the building necessary to comply with the minimum requirements of this chapter; or
   (c)   Within one hundred twenty days after service of the order, plans for the installation of wall anchors in accordance with the requirements specified in subsection 15.07.070.030; or
   (d)   Within two hundred seventy days after the service of the order, acquire permit for the demolition of the building.
   .030   After plans are submitted and approved by the building official, the owner shall obtain a building permit, commence and complete the required construction or demolition within the time limits set forth in Table No. 15.07-B. These time limits shall begin to run from the date the order is served in accordance with subsections 15.07.060.010 and .020.
   .040   Owners electing to comply with subsection .020(c) of this section are also required to comply with subsection .020(b) or .020(d) of this section provided, however, that the two-hundred-seventy-day period provided for in such subsections .020(b) and .020(d) and the time limits for obtaining a building permit, commencing construction and completing construction for complete structural alterations or building demolition set forth in Table No. 15.07-B shall be extended in accordance with Table No. 15.07-C. Each such extended time limit, except the time limit for commencing construction shall begin to run from the date the order is served in accordance with Section 15.07.060.020. The time limit for commencing construction shall commence from the date the building permit is issued. (Ord. 5076 § 1 (part); November 14, 1989.)