10-7-21: TECHNICAL REVIEW COMMITTEE:
The technical review committee shall be headed by the building official and shall include a representative of the town marshal staff and the fire marshal or other designee. At his discretion, the building official may request that other persons from various specific technical disciplines and/or agencies be added to the committee on an ad hoc basis. Except for projects involving interior remodeling only, this committee shall review the technical aspects of all proposed projects for which an application for a building permit has been received. A written report of the review and the committee's recommendations shall be returned to the applicant within a reasonable time, but in no case later than forty five (45) days from the date of application for building permit. No building permit for any project requiring review may be issued by the building official without the review and approval of the committee. (Ord., 6-8-1989; amd. Ord. 2021-O-1, 3-10-2021)