A. Impaired Vertical Clearance. It shall be the responsibility of the permittee to check all underpasses, bridges, overhead wires or other structures for impaired vertical clearance and to bypass or arrange clearance at such locations.
B. Overhead Lines. The permittee must notify the owner of all overhead lines subject to disturbance or damage by his operation at least twenty-four (24) hours in advance of work, and mutually agreeable arrangements must be made between the parties involved.
C. Snooter and Roof Boards. Snooter and roof boards are required from eighteen (18) feet high to above the highest point of load. Any load in excess of twenty (20) feet shall be provided with a means of access to the highest point.
D. Restricted Hours. All loads eighteen (18) feet high or higher shall be moved during the hours of 11:00 p.m. to 5:00 a.m. and may not move from 6:00 a.m. on Saturday until 12:01 a.m. Monday.
E. Pilot Cars. A pilot car displaying signs the same as specified in Section 13.35.070 shall be provided for all loads eighteen (18) feet high or higher.
F. Inspection. Any load eighteen (18) feet or over is subject to inspection by the Engineering Department and must be arranged for twenty-four (24) hours before the scheduled move.