17.130.030 Conditional Use Permit (CUP) Proceedings
   (a)    Minor Conditional Use Permit (CUPm).
      An application shall be filed pursuant to the provisions of Sections 17.100 and this Section of this Zoning Code. Upon acceptance of a Minor Conditional Use Permit (CUPm) application as complete, the Planning Director or his/her designee shall review the application for conformance with the provisions of this Zoning Code. Within thirty (30) days of receipt of a completed application, the Director, or designee, shall prepare and issue a decision letter to the applicant.
   (b)   Conditional Use Permit (CUP).
      An application shall be filed pursuant to the provisions of Sections 17.100 and this Section of this Zoning Code. Upon acceptance of a Conditional Use Permit (CUPm) application as complete, the Planning Director, or his/her designee, shall review the application for conformance with the provisions of this Zoning Code. The Director, or designee, shall review the application for completeness. Once the application has been deemed complete:
      (1)   The Director, or designee, shall prepare a recommendation and forward the recommendation, application, and other relevant materials to the Planning Commission secretary. The secretary shall schedule the matter for public hearing pursuant to the provisions of Chapter 17.100 of this Zoning Code.
      (2)    The Planning Commission shall hear and take action upon the application pursuant to the provisions of Chapter 17.100 of this Zoning Code.
      (3)    The Commission shall act to approve, conditionally approve, or deny the application.
      (4)    The Commission shall adopt a Resolution containing its findings and decisions. The Resolution shall recite, among other things, the facts and reasons which make the granting or denial of the Conditional Use Permit necessary to carry out the provisions and general purpose of this Zoning Code. If the Conditional Use Permit is granted, the report shall recite the conditions and limitations imposed, if any.