(a) Electric, cable television, and telephone service shall be provided within each subdivision. Gas service may be required where reasonably accessible. Whenever such facilities are reasonably accessible and available, they may be required to be installed within the area prior to the approval of the final plat. Telephone, electric, street lighting wires, conduits, and cables shall be constructed underground unless otherwise approved by the Village.
(b) Whenever a sanitary sewer, water main, or storm sewer, and electric and/or telephone line are each placed underground in the same utility easement, the following provision shall be applicable:
(1) The total easement width shall not be less than 20 feet.
(2) The sanitary sewer, water main, or storm sewer shall be installed on one side of the easement.
(3) Electric, gas, cable television, and telephone shall not be installed within 5 feet of either sanitary sewer, water main, or storm sewer.
(4) All utilities shall be extended to the furthest extent of the subdivision for future expansion.