1113.09 SIDEWALKS.
   (a)   Sidewalks shall be required on both sides of all streets except in Industrial.
   (b)   All sidewalks shall be constructed in accordance with the Village of Ada Design Criteria and Construction Standards and Drawings. The developer who constructs a sidewalk is responsible for curb ramps at intersections. Homeowners will be required to install sidewalks on individual properties within six (6) months of finalized building construction (occupation of the building). Two (2) years after that particular phase of the subdivision is accepted, sidewalks must be installed on all lots by whoever owns the properties. If the sidewalks are not installed, the Village will perform the installation and assess the property owner for all cost incurred.